schedule 0.0.0

This is/was the timescale as proposed in the grant application. With the (then unforeseen) delays of the funding process, all this will need to be revised.

intermediate objectives (projected)

initial design phase: september 2007–

Software: design, preliminary implementation and testing of software components.
Analog electronics: design and testing.

break: november 2007
alpha build: february 2008

Software: initial working system.
Electronics: begin final build.
Hardware: begin construction.

break: may–june 2007
beta build: august 2008

Complete working system: testing carried out with beta testers.

final build: november/december 2008
Share
This entry was posted in construction, hardware, schedule, software and tagged , , . Bookmark the permalink. Post a comment or leave a trackback: Trackback URL.

2 Trackbacks

  1. By schedule 0.0.1 – io 0.0.1 beta++ on June 30, 2009 at 11:35 pm

    [...] 0.0.1 beta++ Skip to content about « schedule 0.0.0 enclosures: rack spaces [...]

  2. By schedule 0.0.1 – io 0.0.1 beta++ on January 1, 2010 at 11:27 am

    [...] 0.0.1 beta++ Skip to content aboutsounds « schedule 0.0.0 enclosures: rack spaces [...]

Post a Comment

Your email is never published nor shared. Required fields are marked *

*
*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Arts Council Ireland logo